 "note": "Hand-written information points for the map prototype. Every figure under 'measured' comes from this investigation's own files (results/dem/dem-change-patches-*.csv, results/dem/watershed-*.csv, results/lidar/watershed-kingshill-ponding.csv); every line under 'on record' names its record and is labelled: [C] read in the record itself by this session, [R] from a research note in research/ (subagent-gathered, not re-read here), [U] unverified lead. Survey dates: the 2018 USGS survey was flown mid-2018; the 2024 survey (PR_PuertoRicoUSVI_D24) was flown March 2024 to March 2025. Edited 2026-11-25 (second pass: rates per year; record vs measured).",
 "points": [
  {
   "id": "anguilla",
   "title": "Anguilla landfill, St. Croix",
   "lon": -64.781125,
   "lat": 17.697823,
   "measured": [
    "Ground raised over 77,179 m2 (7.7 ha) between the 2018 and 2024 surveys",
    "Net volume added: about 389,000 m3 (about 509,000 cubic yards)",
    "Average rise 5.0 m; highest rise 18.5 m",
    "Satellite (Sentinel-2) Jan 2019 vs Jan 2025: the bare fill area grew"
   ],
   "record": [
    "[C] VIWMA testimony, 2 Dec 2025: the 2013 consent order required Anguilla to stop accepting waste by 2018 and finish closure construction by 30 June 2020; 'Those deadlines were not met.' (LF-aa793d2ef9d8)",
    "[C] Same testimony: $46 million CDBG-DR to close three-quarters of the landfill and expand the remaining quarter, about five more years; VIWMA-Port Authority lease signed September 2025 (LF-aa793d2ef9d8)",
    "[C] About 30 acres, in use since about 1966, about 117,000 tons a year; design capacity greater than 2.5 million m3 as of 2000 (amended complaint, U.S. v. GVI, 3:10-cv-48, paras. 68 and 73; filed 2010)",
    "[R] Oct 2018 court order asks for briefs on FAA concurrence with the landfill expansion (LF-8987dd16ba89)"
   ],
   "reading": "The ground at the landfill kept rising after the 2018 date by which, under the consent order, it was to stop taking waste. The lidar measures the volume; it does not say what the volume is made of or whether any limit was exceeded.",
   "open": "Tonnage records 2018-2024; the permitted final grades; the FAA airspace determination.",
   "rates": [
    "Volume added: about 57,000-72,000 m3 a year",
    "Average rise: 0.7-0.9 m a year; at the highest point 2.7-3.4 m a year"
   ],
   "compare": [
    {
     "claim": "The 2013 consent order required Anguilla to stop accepting waste by 2018 (VIWMA testimony, 2 Dec 2025)",
     "source": "LF-aa793d2ef9d8",
     "label": "C",
     "ours": "Ground at the landfill kept rising between the mid-2018 and 2024-25 surveys",
     "verdict": "agrees",
     "note": "VIWMA itself says the deadline was not met; the lidar is consistent with that."
    },
    {
     "claim": "About 117,000 tons of waste a year (amended complaint, 2010, para. 68)",
     "source": "U.S. v. GVI, 3:10-cv-48, amended complaint (evidence/supporting/landfill/)",
     "label": "C",
     "ours": "At that rate, 630,000-800,000 tons over the interval would fit into the measured 389,000 m3 only at 1.6-2.1 tons per m3",
     "verdict": "cannot test",
     "note": "1.6-2.1 t/m3 is well above what compacted municipal waste is usually taken to weigh [U]. So less waste went to Anguilla than the 2010 rate, or settlement and excavated cells hide volume. Needs VIWMA's tonnage records for 2018-2024."
    }
   ],
   "type": "landfill"
  },
  {
   "id": "montpellier",
   "title": "Quarry at Estate Montpellier, St. Croix",
   "lon": -64.831116,
   "lat": 17.735185,
   "measured": [
    "Ground lowered over 19,830 m2 (2.0 ha) between the 2018 and 2024 surveys",
    "Net volume removed: about 301,000 m3",
    "Average drop 15.2 m; deepest 46.0 m",
    "Satellite Jan 2019 vs Jan 2025: the pit area expanded"
   ],
   "record": [
    "[R] 'St. Croix Quarry, 1 Estate Montpellier' listed as an aggregates site on Vulcan Materials' business pages",
    "[R] Heavy Materials LLC's OSHA site address: #1 & 5a Montpellier, Frederiksted (LF-7df8ad8b2f8b)",
    "[R] No DPNR mining or earth-change permit found in our archive or on the web (searched 2026-11-25)"
   ],
   "reading": "An active quarry, deepened by up to 46 m in about six years.",
   "open": "The permit and its approved extent and depth.",
   "rates": [
    "Volume removed: about 44,000-56,000 m3 a year",
    "Average deepening 2.2-2.8 m a year; at the deepest point 6.7-8.5 m a year"
   ],
   "compare": [
    {
     "claim": "No public statement of the quarry's permitted extent, depth or output found",
     "source": "our archive and web search, 2026-11-25",
     "label": "R",
     "ours": "Deepened by up to 46 m; about 301,000 m3 removed",
     "verdict": "cannot test",
     "note": "A DPNR earth-change or mining permit would set the approved limits."
    }
   ],
   "type": "quarry"
  },
  {
   "id": "sandy-point",
   "title": "Sandy Point beach, St. Croix",
   "lon": -64.9,
   "lat": 17.681,
   "measured": [
    "A band built up over 93,526 m2 (net about +154,000 m3; up to 4.1 m)",
    "A band cut back over 74,418 m2 (net about -145,000 m3; up to 3.8 m)",
    "Satellite 2018 vs 2024: the shape of the point changed"
   ],
   "record": [
    "[R] Studies (Boulon, Dutton & McDonald 1996; DPNR 2018) describe a yearly cycle of erosion and rebuilding on this beach",
    "[R] The 2023 Coastal Vulnerability Index notes the USVI had no shoreline-change dataset (LF-a7b825646a58)"
   ],
   "reading": "The beach moved between the two surveys. Two dates cannot tell a seasonal swing from a trend.",
   "open": "More dates (imagery or lidar) to separate season from trend.",
   "rates": [
    "Built-up band: about 22,000-28,000 m3 a year; cut band: about 21,000-27,000 m3 a year",
    "Two dates only: a yearly rate here mixes the seasonal swing with any trend"
   ],
   "compare": [],
   "type": "beach"
  },
  {
   "id": "hwy64-bridge",
   "title": "Route 64 East Airport Road Bridge",
   "lon": -64.787296,
   "lat": 17.707528,
   "measured": [
    "Our largest Hwy 64 gut crossing: about 1,076 ha of ground drains to it",
    "The bare-earth model shows the road here as a dam, because it cannot see the bridge opening",
    "Ground raised up to 5.6 m (average 1.6 m) over about 1,600 m2, 34 m from the bridge, and 1.2 m over 620 m2, 32 m away, between the 2018 and 2024 surveys"
   ],
   "record": [
    "[C] The bridge is a site of FHWA Emergency Relief project VI ST ER STX(003), post-Maria storm repairs, 15 St. Croix sites, design-build by VI Paving for DPW (CZM application, July 2022, LF-58732aa29818)",
    "[C] Its flood hazard permit report (July 2022) places it at 17 42' 27.0\" N, 64 47' 14.4\" W, along Highway 64 just north of Route 66, within about 5 m of our crossing; the plan replaces the bridge slightly east and raises the road (LF-c6661af78abc)"
   ],
   "reading": "The first lidar crossing matched to a named official structure. The same project lists 14 more St. Croix gut, culvert and road sites to test the same way.",
   "open": "Test the other 14 sites.",
   "rates": [],
   "compare": [
    {
     "claim": "Bridge position in the FHWA ER flood hazard permit report: 17 42' 27.0\" N, 64 47' 14.4\" W",
     "source": "LF-c6661af78abc",
     "label": "C",
     "ours": "Our largest Hwy 64 gut crossing lies within about 5 m",
     "verdict": "agrees",
     "note": ""
    },
    {
     "claim": "The repair plan replaces the bridge slightly east of the old one and raises the bridge and road, which sat five to ten feet below the roads around it",
     "source": "Flood hazard permit report, Rt. 64 East Airport Bridge, July 2022 (LF-c6661af78abc), sections 3.00 and 4.00",
     "label": "C",
     "ours": "Raised ground of up to 5.6 m beside the bridge between the surveys",
     "verdict": "agrees",
     "note": "Consistent with the road being raised; when the work was done is not in our records, so this is not proof the repair was built before the 2024 survey."
    }
   ],
   "type": "bridge"
  },
  {
   "id": "cottage",
   "title": "Cut and fill at Barren Spot / Cottage, St. Croix",
   "lon": -64.760295,
   "lat": 17.721871,
   "measured": [
    "Raised over 24,148 m2 (net about +145,000 m3; up to 18.3 m)",
    "Lowered over 26,821 m2 (net about -114,000 m3; up to 8.5 m)",
    "Satellite: a bare industrial yard in both years"
   ],
   "record": [
    "[U] Possibly Heavy Materials' concrete plant at 9010 Estate Cottage (OSHA record LF-28c1a7265eae); not matched to the site"
   ],
   "reading": "Material moved within one yard: dug on one side, piled on the other.",
   "open": "Who operates the site; whether it is a stockpile yard.",
   "rates": [
    "Piled: about 21,000-27,000 m3 a year; dug: about 17,000-21,000 m3 a year"
   ],
   "compare": [],
   "type": "earthworks"
  },
  {
   "id": "kingshill-ponding",
   "title": "Water held at Unity St / Hwy 65, Kingshill",
   "lon": -64.794781,
   "lat": 17.727293,
   "measured": [
    "About 3,300 m2 where the ground model holds water against the road embankment, up to 1.7 m deep (about 3,000 m3)",
    "The main gut runs beside Hwy 65 for about half a kilometre here"
   ],
   "record": [
    "[R] The 2000 VITEMA flood plan names 'Upper Bethlehem/Body Slob' near John Woodson Junior High as a flood spot (LF-9d5227c5f1d9); whether it is this spot is not shown"
   ],
   "reading": "Water has to cross the road here to drain: through a culvert the lidar cannot see, or over the road.",
   "open": "DPW culvert records for this crossing; flood reports.",
   "rates": [],
   "compare": [],
   "type": "drainage"
  },
  {
   "id": "midland-bridge",
   "type": "bridge",
   "title": "Route 72 Midland Road bridge, St. Croix",
   "lon": -64.798139,
   "lat": 17.739139,
   "measured": [
    "Our gut crossing on Hwy 72 lies 9 m from the permit report's coordinate; about 252 ha drains to it",
    "The federal bridge inventory has a Route 72 bridge over an unnamed gut, built 1920, 16 m away",
    "Ground lowered by about 1.9 m (up to 3.0 m) over 388 m2, 6 m from the site, between the 2018 and 2024 surveys"
   ],
   "rates": [],
   "record": [
    "[C] A site of FHWA Emergency Relief project VI ST ER STX(003), post-Maria storm repairs, 15 St. Croix sites, design-build by VI Paving for DPW (CZM application, July 2022, LF-58732aa29818)",
    "[C] Its flood hazard permit report places it at 17 44' 20.9\" N, 64 47' 53.3\" W (LF-cea82f59db00)"
   ],
   "compare": [
    {
     "claim": "Bridge position in the permit report: 17 44' 20.9\" N, 64 47' 53.3\" W",
     "source": "LF-cea82f59db00",
     "label": "C",
     "ours": "Our largest crossing here lies 9 m away",
     "verdict": "agrees",
     "note": ""
    }
   ],
   "reading": "A second post-Maria bridge repair site that the lidar's drainage model finds on its own. The lowered ground beside it may be channel or bridge work.",
   "open": "What the repair changed, and when it was built (before or after the 2024 survey)."
  },
  {
   "id": "chenay-bay",
   "type": "bridge",
   "title": "Route 82 at Chenay Bay culverts, St. Croix",
   "lon": -64.657639,
   "lat": 17.757194,
   "measured": [
    "Our gut crossing on Hwy 82 lies 20 m from the permit report's coordinate; about 139 ha drains to it",
    "The ground model holds water against the road 17 m away (about 19,100 m2, up to 1.2 m deep): a culvert the model cannot see"
   ],
   "rates": [],
   "record": [
    "[C] A site of FHWA Emergency Relief project VI ST ER STX(003), post-Maria storm repairs, 15 St. Croix sites, design-build by VI Paving for DPW (CZM application, July 2022, LF-58732aa29818)",
    "[C] Its flood hazard permit report places it at 17 45' 25.9\" N, 64 39' 27.5\" W (LF-04b16ec99cf4)"
   ],
   "compare": [
    {
     "claim": "Site position in the permit report: 17 45' 25.9\" N, 64 39' 27.5\" W",
     "source": "LF-04b16ec99cf4",
     "label": "C",
     "ours": "Our crossing lies 20 m away",
     "verdict": "agrees",
     "note": ""
    }
   ],
   "reading": "A culvert repair site where the lidar shows a gut meeting the coast road and water backing up behind it.",
   "open": "The culvert's size against the 139 ha that drain to it."
  },
  {
   "id": "altona-lagoon",
   "type": "bridge",
   "title": "Route 7532 Altona Lagoon box culverts, St. Croix",
   "lon": -64.695944,
   "lat": 17.749833,
   "measured": [
    "No gut crossing here in our model (nearest 387 m): the culverts link a lagoon, not a gut, so the drainage model has no channel to find",
    "Ground lowered by about 1.0 m (up to 2.2 m) over 783 m2, 17 m from the site, between the 2018 and 2024 surveys"
   ],
   "rates": [],
   "record": [
    "[C] A site of FHWA Emergency Relief project VI ST ER STX(003), post-Maria storm repairs, 15 St. Croix sites, design-build by VI Paving for DPW (CZM application, July 2022, LF-58732aa29818)",
    "[C] Its flood hazard permit report places it at 17 44' 59.4\" N, 64 41' 45.4\" W (LF-73290e0f2eb7)"
   ],
   "compare": [],
   "reading": "A repair site the drainage model is not built to find (tidal lagoon flow). The lowered ground beside it may be channel work.",
   "open": "What the repair changed and when."
  }
 ],
 "interval_note": "Yearly rates divide the change by the time between the two surveys. Until each site's exact flight dates are read from the lidar points, that time is a range: 5.4 years (2018 survey's last flights, 19 Oct 2018, to the 2024 survey's first, 13 Mar 2024) to 6.8 years (13 May 2018 to 16 Mar 2025). Each rate is given as low-high over that range; it is an average, not a constant pace.",
 "types_note": "type: landfill | quarry | beach | bridge | earthworks | drainage (the map's filter chips)."
}